Case ref:201105126
-
Date:October 2012
-
Body:South Lanarkshire Council
-
Sector:Local Government
-
Outcome:No decision reached
-
Subject:capital works, renovation, central heating, double glazing, etc
Summary
Mrs C raised a number of issues about the siting of a new boiler house close to her property. This was as part of works being carried out by the council to replace the heating system serving a multi-storey block. In particular, Mrs C complained about the consultation process which led to the positioning of the boiler house.
However, before we completed our investigation, Mrs C contacted us and withdrew her complaint. We, therefore, did not reach a decision on it.